2025 West Carleton-March Road Resurfacing Update (May 15)
- Ward 5 Staff
- 13 hours ago
- 1 min read
We received an updated schedule on Wednesday afternoon and wanted to update you on the following road resurfacing projects in West Carleton-March
Thomas A Dolan Pkwy from Marchurst Rd to Dunrobin Rd (OR 9): Pulverizing completed west of Dunrobin Community Center and granular base applications are ongoing, paving to follow. Milling Dunrobin to Community Center section anticipated week May 19th-2025
Marchurst Rd from Thomas A. Dolan Pkwy to Murphy Side Rd : Pulverizing ongoing followed by granular road base applications this week.
Murphy Side Rd from Marchurst Rd to Dead End: Pulverizing to follow pulverizing completion on Marchurst
Kinburn Side Rd (OR 20) from 50m east of Timmins Rd to Upper Dwyer Hill Rd (OR 3): Contractor Mobilizing this week. Pulverizing of Kinburn anticipated week of May 19th-2025.
Kinburn Side Rd (OR 20) from 20m East of Upper Dwyer Hill Rd (OR 3) to 160 M east of Upper Dwyer Hill Rd (OR 3): Contractor Mobilizing this week. Milling anticipated week of May 26th-2025.
Shaw Rd from Lunney Rd to OR 29 (Former Hwy 15): The week of May 26th -2025 the Contractor anticipating mobilizing warning signs and barrels to site. The following week Construction is anticipated to start.
March Valley Rd (Fourth Line) from Cameron Harvey Dr (OR 109) to Klondike Rd: The week of June 23th -2025 the Contractor anticipating mobilizing warning signs and barrels to site. The following week Construction is anticipated to start.
Moonstone Rd from Rothbourne Rd to Dead End.: The week of July 28th -2025 the Contractor anticipating mobilizing warning signs and barrels to site. The following week Construction is anticipated to start