top of page

2025 West Carleton-March Road Resurfacing Update (May 15)

We received an updated schedule on Wednesday afternoon and wanted to update you on the following road resurfacing projects in West Carleton-March

 

  • Thomas A Dolan Pkwy from Marchurst Rd to Dunrobin Rd (OR 9):  Pulverizing completed west of Dunrobin Community Center and granular base applications are ongoing, paving to follow. Milling Dunrobin to Community Center section anticipated week May 19th-2025


  • Marchurst Rd from Thomas A. Dolan Pkwy to Murphy Side Rd :  Pulverizing ongoing followed by granular road base applications this week.


  • Murphy Side Rd from Marchurst Rd to Dead End: Pulverizing to follow pulverizing completion on Marchurst


  • Kinburn Side Rd (OR 20) from 50m east of Timmins Rd to Upper Dwyer Hill Rd (OR 3): Contractor Mobilizing this week. Pulverizing of Kinburn anticipated week of May 19th-2025.


  • Kinburn Side Rd (OR 20) from 20m East of Upper Dwyer Hill Rd (OR 3) to 160 M east of Upper Dwyer Hill Rd (OR 3): Contractor Mobilizing this week. Milling anticipated week of May 26th-2025.


  • Shaw Rd from Lunney Rd to OR 29 (Former Hwy 15): The week of May 26th -2025 the Contractor anticipating mobilizing warning signs and barrels to site. The following week Construction is anticipated to start.


  • March Valley Rd (Fourth Line) from Cameron Harvey Dr (OR 109) to Klondike Rd: The week of June 23th -2025 the Contractor anticipating mobilizing warning signs and barrels to site. The following week Construction is anticipated to start.


  • Moonstone Rd from Rothbourne Rd to Dead End.: The week of July 28th -2025 the Contractor anticipating mobilizing warning signs and barrels to site. The following week Construction is anticipated to start



bottom of page